The next step is for volunteers to begin putting on the "tar paper" and metal roofing.
The latest information, news, views, entertainment, and lots of music - presented by Living Word Lutheran Church in Spicer, Minnesota.
Wednesday, June 27, 2012
Monday, June 25, 2012
June 25: Trusses Went Up This Morning
The guys from Oak Ridge Construction set the roof trusses in place this morning (with help from a crane - not pictured). They will start on the roof sheathing boards late today or tomorrow. Praise God for more good construction weather!
Sunday, June 24, 2012
From the LCMS Office of the President
|
Thursday, June 21, 2012
June 21 - Ready for the Floor
The roof trusses were delivered today (If you look closely you can see them in the distance, stacked near the church in the photo of the sign).
Oak Ridge Construction will be setting the trusses on the walls on Monday (weather permitting).
Plans are for our volunteers to begin installing the metal roofing late afternoon and evening next Wednesday (June 27). Drop a note in the comments (or text pastor@livingwordlutheran.net) if you can help us with this. Thanks.
Oak Ridge Construction will be setting the trusses on the walls on Monday (weather permitting).
Plans are for our volunteers to begin installing the metal roofing late afternoon and evening next Wednesday (June 27). Drop a note in the comments (or text pastor@livingwordlutheran.net) if you can help us with this. Thanks.
Wednesday, June 20, 2012
June 20 - Walls Are Up !
Several views of the church building walls. Praise God for the couple-day delay that caused to the walls to be put up after, not before, Sunday's storm. If you have a chance, take a drive out to the building site and walk around inside the church.
Tuesday, June 19, 2012
Sunday, June 17, 2012
Wall Sections Delivered
The SIPs (Structural Insulated Panels) arrived on Thursday. They look like Giant Vanilla Oreos - thick white foam sandwiched between two OSB boards. Weather permitting, Oakridge Construction will be setting these wall panels in place this week.
Friday, June 15, 2012
June 15 - The Floor is Poured
Joe Caskey Masonry and New London Concrete providing the manpower and materials for the church floor!
Saturday, June 9, 2012
Thursday, June 7, 2012
Cleaning Up God's Creation
Last evening nine of us waded through the knee-high thistles that infest our adopt-a-highway section. (Try doing that in flip-flops - Eve did!) Our goal was to do our part to clean up a small part of God's creation. Thanks to Carrie, Tyler, Terrell, Bryson, Eve, Phil (left to right in the picture!. Thanks also to Tim, Mike and Pastor Dave who aren't pictured. We all have one simple reminder: It really isn't a hardship to keep stuff in your car until you can toss it in the garbage can at home or the gas station next time you fill up. It's just the right thing to do.
Wednesday, June 6, 2012
June 6: Heating Rough-in Completed
Nothing "exciting," but simply more good progress going smoothly. Darryl Sanderson of Riverview Refrigeration completed the heat-duct rough-in. The duct work will be covered by the cement slab (floor) which could be poured later this week.
Praise God!
Pastor David
Praise God!
Pastor David