Friday, July 27, 2012

July 26 - Lots of new stuff

I've been out of town on vacation for a couple of weeks, so there's lots of new stuff for this update:

+ Interior walls have been completed

+ Ceiling has drywall has been hung

+ Aprons have been poured in front of each entrance

+ Windows have been installed

You can see all of these developments in the pictures below.

The next work to be completed will be drywall on the interior walls.

Thursday, July 12, 2012

July 11- Roof Finished. Inside Walls Going Up

Our volunteers finished putting the steel roofing on the south roof this past Saturday. More volunteers are putting up interior walls on the east end of the building tonight. Most of the black dirt for the lawn has been filled in around the building.

Sunday, July 1, 2012

June 30 - The North Roof is Finished

On Saturday Jason Miller, Vern Samuelson, Bryson Wachter, Brent Sawatzky, Pastor Dave and Kevin Welsh put the metal roofing on the north side of the building. You can't tell it from the photos, but the color is a Charcoal Gray. 

June 28 - Electricity and Water

Workers from Thein Well began drilling the well.  The guys from Electrical Plus have the transformer installed and electricity into the building

June 27 - We start work on the roof

Most of the contractor work on the building is completed. Today Living Word members and friends began work on the roof.